Milling & Paving Project Continues In Valley Woods Next Week

Work will be done on Persimmon and St. Andrews.

(Greendale, Ind.) – A milling and paving project is rolling on in Greendale.

City manager Steve Lampert says O’Mara Construction is planning to complete milling operations on Persimmon and St. Andrews in Valley Woods on Tuesday, November 10, weather permitting.

Paving is scheduled to be completed the same week between November 11-13.

During paving operations, there will be longer periods of time, likely two to three hours, that the pavement will not be drivable.

O’Mara will have staff in place to direct traffic.

RELATED STORIES

Paving Project Begins Tuesday In Greendale

More from Local News


Events

Union Ridge Road to Close at North Hogan Road Intersection

A temporary closure will take place later this month.

Railyard Bar & Grille to Close After Five Year Run

There is still time to enjoy your favorite meal at the Sunman establishment.

Local Sports Report - June 9, 2025

The IHSAA Boys Golf State Tournament continued on Monday.

Longtime Conner HS Football Coach Passes Away Unexpectedly

Our condolences to the Trosper family and the Conner HS community.

On Air

Rick Bernius playing
Josh Turner - Firecracker

Fox News Fox News National Newscast 15:03
Montgomery Gentry Lonely And Gone 14:59
Brett Eldredge Wanna Be That Song 14:56
Doug Stone Warning Labels 14:52