Runway 9/27 will be closed for approximately six weeks.

Shutterstock photo.
(Erlanger, Ky.) – The longest and most utilized runway at Cincinnati/Northern Kentucky International Airport is closed for a rehabilitation project.
Runway 9/27 was closed Monday as CVG is moving forward with critical infrastructure projects in 2021.
The rehab project will consist of new asphalt, concrete, and lighting updates. The work is expected to take one year to complete, requiring a six-month closure of Runway 9/27.
CVG said in a news release Monday that a project of this magnitude typically takes two years to complete.
The project is part of a $69 million investment made by CVG to improve their infrastructure.
“We are grateful for the support and patience of the community and all partners involved as this important infrastructure update is completed,” said Candace McGraw, chief executive officer, CVG. “This project among others will position CVG well for pandemic recovery and future growth.”
For more information, visit www.cvgairport.com.


Lawrenceburg Library to Host Free Halloween Sensation Event
ISP Offer Halloween Safety Tips
Connersville Photographer Charged with Multiple Federal Child Exploitation Crimes
Daylight Saving Time Ends This Weekend
Free Admission to DNR Properties for Veterans, Active-Duty Military on Veterans Day
Batesville HS Among Schools to Earn First-Ever Indiana Blue Ribbon Designation