Buckled Pavement Repairs Begin Friday in Dillsboro

Thursday, July 14, 2022 at 9:44 AM

By Indiana Department of Transportation, news release

The work will require lane closures on U.S. 50.

Shutterstock photo.

(Dearborn/Ripley County, Ind.) - Indiana Department of Transportation contractor Paul H. Rohe Company plans to begin work on or after Friday, July 14, to repair concrete pavement along U.S. 50 in Ripley and Dearborn Counties. Sections of pavement recently buckled near Dillsboro due to hot temperatures causing it to expand.

Starting as early as Friday, contract crews will close the right eastbound lane of U.S. 50 to begin sawcutting and sealing expansion joints. Lanes will close in sections for multiple miles at a time. The closures will move as work progresses. Once work is complete on eastbound U.S. 50, the contractor will move to westbound lanes.

The limits of the repair work is from just west of S.R. 101 to west of Aurora near Dutch Hollow Road. The speed limit will be reduced to 45 mph through the work zone. Repairs are expected to be complete by mid-August, weather permitting.

INDOT reminds drivers to slow down, avoid distractions, and consider worker safety when traveling through active construction zones. All work is weather-dependent, and schedules are subject to change.

U.S. 50 - Ripley/Dearborn Co.

More from Local News

Events

Dearborn County Flooding Update

Clean up days are Friday April 11, Saturday April 12, and Sunday April 13 at 10AM.

Closure planned on State Road 62 in Ripley County

The closure is due to a culvert replacement.

99th Birthday Celebration Set for Dearborn Co. WWII Veteran

The event takes place Friday at the Lawrenceburg Eagles.

Local Sports Report - April 8, 2025

Report missing stats and scores to news@eaglecountryonline.com

Local Sports Report - April 7, 2025

Report missing stats and scores to news@eaglecountryonline.com

On Air

Kenny Chesney Don't Blink 4:45
Terri Clark Now That I Found You 4:41
Miranda Lambert Run 4:38