INDOT: Normal Traffic Patterns Resume On U.S. 50 This Week

Tuesday, July 23, 2019 at 8:30 AM

By Indiana Department of Transportation, news release

The "white top" project between Aurora and Dillsboro is almost complete.

(Dearborn County, Ind.) - Eastbound traffic returned to the eastbound side of U.S. 50 Friday night following completion of a $21.6 million concrete overlay project west of Aurora, from S.R. 101 to just west of S.R. 350.

Westbound traffic will remain restricted until later this week when pavement markings are complete.

Subsequent repair and clean-up work will begin the week of August 8, weather permitting, and will require lane closures at various locations along the route. This work is expected to be complete in approximately two to three weeks.

Motorists are encouraged to watch for crews and continue using caution along the route until all work is complete.

More from Local News


Events

Sunman-Dearborn Schools Share New Facility Upgrades

Some exciting projects have been complete or are ongoing.

Southeastern Career Center Welcomes New Principal

The SCC serves 11 schools districts.

2025 Team Preview: Milan Aims to Build off Sectional Championship Season

The Indians start their season at home vs. Rushville on Aug. 22.

Milan's Ayden Potts Wins Lakeside 5K

Four SIRC races down, two to go.

On Air

Exile Hang on to Your Heart 2:13
Jordan Foster They All Do 2:08
Mark Chesnutt Too Cold At Home 2:05
Kane Brown Backseat Driver 2:01