Design Changes Made to Dry Fork Road Bridge Rehab Project

Tuesday, March 24, 2026 at 7:25 AM

By Ohio Department of Transportation, news release X @eagle993

The plan will balance the construction schedule, and reduce the number of days the road will be closed.

Shutterstock photo.

(Harrison, Oh.) - Despite some unforeseen delays in material delivery that would affect the overall timeline for the Interstate 74/Dry Fork Road bridge rehabilitation, the Ohio Department of Transportation, the city of Harrison and their contractors have developed a plan that will not only balance the construction schedule, but will reduce the number of days Dry Fork Road will be closed.

Following award of the construction contract to the Eagle Bridge Company, the contractor placed orders for the required bridge beams.

However, the beam delivery timing did not align with the original project schedule due to production runs by the manufacturer. As a result, the delivery will occur later than anticipated, impacting the originally planned schedule to close Dry Fork Road earlier in the project.

After identifying the delivery delay, representatives from ODOT, Eagle Bridge, the city of Harrison, and TEC Engineering - the design consultant for the project - met to evaluate options with two priorities: complete the project as efficiently as possible and limit impacts to the Harrison community.

To accomplish these goals, it was decided to pursue a redesign of the piers that will allow the contractors to continue working while waiting for the beams to be fabricated and delivered. Doing so will keep the project moving forward and reduce the duration of the closure of Dry Fork Road from 180 to 150 days.

By shifting major construction activity into later in the year, Dry Fork Road is now anticipated to be closed in early to mid-July, and the closure will be in place until early or mid-December, depending on the date of closure.

The interchange ramps will also be subject to closure at various times while Dry Fork Road is closed, but these closures will not be concurrent. Although a schedule has yet to be outlined, the westbound I-74 exit and entrance ramps will be closed first for up to 45 days, and once the reconstruction work is completed, the I-74 eastbound on and off ramps at Dry Fork Road will be closed for 45 days. 

The Dry Fork Road project includes widening the bridge over I-74 to add turn lanes at the I-74 on-ramps; constructing a sidewalk along the bridge; widening the westbound I-74 off-ramp; and rebuilding the traffic signals at the ramps.

The Eagle Bridge Company was awarded a contract in the amount of $8.25 million to complete the project, and although the project will be substantially complete by the end of this year, all work is scheduled to be completed in late spring of 2027.

More from Local News

Events

Ken Maddin to Appear on Wheel of Fortune

The episode airs this week.

Bridge Deck Overlay Project to Begin on U.S. 52 in Brookville

The project will run into late August.

Town of Dillsboro Announces Sanitary Sewer Cleaning and Inspection Project

Work is scheduled to begin on Thursday, March 26.

Seven SEI Hoops Stars Earn All-State Honors

The recognition comes from the Indiana Basketball Coaches Association.

East Central's Mayer Named Hasbrook Family Leadership Award Recipient

The scholarship is administered through the IHSAA.

Batesville Teams Place at NASP State Tournament

Several area school teams have qualified for nationals.

On Air

Your Hometown Radio Station playing
Ashley McBryde - One Night Standards

David Allan Coe You Never Called Me By My Name 2:19
Blake Shelton Blake Shelton - Austin - Eagle Only 2:15
Cody Johnson Dirt Cheap 2:11
Kenny Chesney Bar at the End of the World 2:07