Bridge Work Planned Along U.S. 52 in Franklin County

Construction to begin on or after April 9.

INDOT Map

(FRANKLIN COUNTY, IN) — The Indiana Department of Transportation contractor Paul H. Rohe Company plans to reduce U.S. 52 to one lane over Big Cedar Creek on or after April 9 to begin bridge rehabilitation work in Franklin County.

The construction will be north of Cedar Grove. There will be temporary traffic signals while construction is in progress. Signage will begin to be placed in the area prior to the start of the construction.

This project is part of a $1.5 million contract awarded to Paul H. Rohe in December 2023. It is expected to be complete by early November.

INDOT reminds drivers to slow down, use extra caution and avoid distractions when traveling near work zones. All work is weather-dependent, and schedules are subject to change.

More from Local News

Events

Riehle Wins Bulldog Chase 5K; Hatton & Detmer are Overall SIRC Champs

Batesville played host to the sixth and final race on Saturday.

East Central Soccer Unveils New Turf Field

The start of the season is right around the corner.

SD's Ballart Ready to Sign with U of L

Ballart received his official offer this month after being verbally committed since last September.

On Air

Your Hometown Radio Station playing
Garth Brooks - Ain't Going Down (Til The Sun Comes Up)

Jordan Foster They All Do 3:29
Megan Moroney Tennessee Orange 3:25
Mark Chesnutt I'll Think of Something 3:21
Matt Stell Breakin In Boots 3:19